Civil100%
Site Preparation & Foundation
Site levelling, hoarding, excavation, slope protection, base slab waterproofing and basement pile cap works are complete.
Civil100%
Main Structure
Basement structure, beams, columns, floor casting, roof structure and structural acceptance are complete.
Civil100%
Masonry & Secondary Structure
Internal and external masonry, construction columns, lintels, sill caps, opening closure and wall mesh works are complete.
Civil98%
Internal & External Plastering
Layered plastering, anti-crack external plaster, corner straightening and tie-rod hole sealing are close to completion.
Civil80%
Roof Works
Roof fall formation, waterproofing, protection layer, insulation and edge closure details are progressing.
M&E60%
Water Supply & Drainage
Water pipe embedding, drainage reservations, kitchen and bathroom risers, balcony drainage and roof drainage are under active installation.
M&E30%
Power & ELV Systems
DB box preparation, ELV box preparation, conduit pulling, common-area electrical risers and cable trays are progressing.
Fit-Out25%
Fit-Out Handover
Civil work areas are being handed over for fit-out, with hollow-area correction, measurement checks, setting-out and floor-level review.
Fit-Out70%
Fit-Out M&E Modification
Point checks, wall chasing, wiring upgrades, kitchen and bathroom water-route optimisation and position adjustments are advancing.
Fit-Out30%
Kitchen & Bathroom Waterproofing
Base levelling, multi-layer waterproof coating, ponding-test preparation and protection works are moving forward.
Fit-Out30%
Central Air-Conditioning
Indoor unit fixing, copper pipe connection, insulation wrapping, condensate drainage and air outlet positioning are in progress.
Fit-Out20%
Ceiling Substrate
Living and dining ceiling framing, flat ceilings, curtain boxes, corridor ceilings and anti-crack details are being carried out.
Fit-Out30%
Floor Levelling / Timber Floor Base
Fine floor screed, moisture protection, base grinding and flatness checks are being prepared for later finish layers.